You willA stair worked out from the height between two levels, a ramp and a railing, each checked against your design codes as you change it.
Time6 min
Why it mattersRisers and goings follow from the floor to floor height, so they are calculated and checked, not typed and hoped for.

Try it in Plotlay → Opens an example project with this lesson beside it. Nothing to install.

Steps

  1. Give the levels their heights first: open Levels and set each floor’s elevation (Ground 0, Level 1 at 2.85 m, for example). A stair climbs from its own level to the next one up.
  2. In the Building workspace choose Add › Stair on the quick strip (in Easy: Draw, then Stair) and pick a layout: straight, L with a quarter landing, L with winders, U with a half landing, or spiral.
  3. Click the foot of the stair (the middle of its bottom riser), then click which way it goes up. It appears at its real size, with the number of risers, each riser and each going worked out from the height.
  4. Select the stair. Stair design shows the risers, riser height, going, two risers plus a going and the pitch. Type a width, a going or a riser count to set it yourself; leave a box blank and it is worked out again.
  5. Read the check under the figures: each rule of the design codes you have on shows green, amber or red with its limit and clause, and the codes’ check-by-hand items (headroom, landings, handrails) are listed in their own words.
  6. Under Floor above, keep Open over the whole stair, or choose Open where a head needs it and type the headroom to keep. Then Guard the opening upstairs puts a balustrade round it, left open where the flight steps off.
  7. For a ramp, choose Ramp, type the height it climbs and its gradient, click the low end and then the way up. For a balcony or deck edge, choose Railing, click along the line and Finish.

Tips

  • Give a ramp’s Longest run your code’s figure to split it into equal runs with landings between.
  • Change a level’s height and choose the stair again: it is worked out for the new height with its foot where it was.
  • With a design code on, the going and riser Plotlay picks sit inside that code’s ranges. With none on, it starts from a 175 riser and a 250 going and checks nothing.
  • The stair shows cut on a section when a section line passes along it, and each stair, ramp and railing has a row in the schedules.
  • An agent does the same with design_stair, design_ramp, add_railing and check_stair.

Common mistakes

  • Placing a stair before the levels have heights: with no level above, Plotlay asks for the height it climbs.
  • Reading a green check as approval. The codes are reference only: the certifier and the current code decide.
  • Expecting ramps to pass or fail. Most codes describe ramps in words, so the ramp’s own gradient and lengths are shown beside the code’s text for you to compare.
Check yourself

Level 1 moves from 2.85 m to 3.1 m above the ground floor. What happens to a stair Plotlay worked out?

Words in this lesson

Workspace
Site, Building, Capture or Documents in the top bar. A workspace changes which tools come first; it never hides anything in the project.
Schedule
A table drawn from the plan: rooms and finishes, doors, windows, plants or materials. It updates as the plan changes and downloads as CSV.
Elevation and section
An elevation is a side of the house, or a wall from inside, drawn straight on. A section is a cut through the building along a line you place.
Design code
A set of planning or building rules for a place, such as a state’s planning code, built into Plotlay as a pack of checks. Choose the codes that apply to each project.

Related lessons